Key takeaways
- Bars a city or county from approving a discretionary or ministerial permit or other entitlement for building a data center, or expanding one in a way that raises maximum peak water use, unless the applicant has supplied prescribed information, including a water scarcity plan and a water supply assessment.
- The applicant must also take responsibility for the full cost of any water conveyance, treatment, storage or distribution improvements the water supplier says are needed.
- The Legislature finds this is a statewide concern that reaches charter cities.
AB 2469 — Ch. 436, Stats. 2026. This guide is written for California local government staff and distinguishes the law's direct requirements from source commentary and possible local implications.
At a glance
| Bill and chapter | AB 2469 · Ch. 436, Stats. 2026 |
|---|---|
| Subject area | Environmental Quality (Water, Energy, Waste, Climate) |
| Local impact | Limits or preempts local authority |
| Action class | Code and operational |
| Workbook priority | 4.0 (scale: 5 highest) |
| Effective date | Jan 1, 2027 (general effective date; the digest states no separate operative date) |
| Who is affected | All cities and counties, including charter cities |
What the measure changes
Bars a city or county from approving a discretionary or ministerial permit or other entitlement for building a data center, or expanding one in a way that raises maximum peak water use, unless the applicant has supplied prescribed information, including a water scarcity plan and a water supply assessment. The applicant must also take responsibility for the full cost of any water conveyance, treatment, storage or distribution improvements the water supplier says are needed. The Legislature finds this is a statewide concern that reaches charter cities.
The chaptered bill text controls; the Legislative Counsel’s Digest is a summary of the statute. This article translates the workbook’s findings into an implementation-focused overview and does not replace the statute or jurisdiction-specific legal advice.
Who this matters to in city or county government
Covered entities and scope: All cities and counties, including charter cities
Population or other scope limit: New data centers and expansions that increase maximum peak water use
Departments and roles identified in the workbook:
- Planning/Zoning
- Building/Permits
- Utilities (Water/Wastewater/Solid Waste/Energy)
- City/County Attorney
- Economic Development
- Finance/Treasury/Tax
Charter-city note: Applies (statewide concern declared)
What local governments need to know
Planning and building staff: add to data center application checklists the water scarcity plan, water supply assessment and other prescribed information, plus a showing that the applicant will pay the full cost of water conveyance, treatment, storage or distribution improvements set by the water supplier, and withhold discretionary or ministerial approval until these are provided. Amend zoning and permit procedures and cost-recovery fees; coordinate with water suppliers.
Code or governing-body change: Amend zoning and permit procedures to bar data center approvals or water-intensive expansions until the applicant supplies a water scarcity plan, water supply assessment and other required information, and update cost recovery fees.
Operational change: Planning and building add the required water items and the applicant's commitment to fund supplier-required water improvements to checklists, withhold approvals until complete, and coordinate with water suppliers.
Code review: Yes
Potentially affected code or policy areas: Zoning (data centers); Discretionary and ministerial permit procedures; Application checklists; Development fees and cost recovery; Water supply coordination
Preemption or local authority: Yes
New local requirement: Yes
Implementation roadmap
- Confirm the agency is covered: All cities and counties, including charter cities Scope limits: New data centers and expansions that increase maximum peak water use
- Assign a lead and supporting roles from the affected departments: Planning/Zoning, Building/Permits, Utilities (Water/Wastewater/Solid Waste/Energy), City/County Attorney, Economic Development, Finance/Treasury/Tax.
- Review the relevant code, ordinance, plan, fee schedule, or governing-body policy: Amend zoning and permit procedures to bar data center approvals or water-intensive expansions until the applicant supplies a water scarcity plan, water supply assessment and other required information, and update cost recovery fees.
- Update staff workflow, forms, notices, contracting, reporting, or training as applicable: Planning and building add the required water items and the applicant's commitment to fund supplier-required water improvements to checklists, withhold approvals until complete, and coordinate with water suppliers.
- Calendar and verify the applicable dates: Jan 1, 2027 (general effective date; the digest states no separate operative date)
Key dates and deadlines
- General effective date and deadlines: Jan 1, 2027 (general effective date; the digest states no separate operative date)
- Code change deadline: Jan 1, 2027
Implementation and compliance considerations
| Implementation area | Review | What staff should verify |
|---|---|---|
| Local impact classification | Limits or preempts local authority | Workbook action class: Code and operational. |
| Scope and coverage | Confirm | New data centers and expansions that increase maximum peak water use |
| Effective dates | Calendar | Jan 1, 2027 (general effective date; the digest states no separate operative date) |
Enforcement and reimbursement
None stated; state-mandated local program, no reimbursement required for a stated reason; the infrastructure cost provision is severable
Issues to confirm with agency counsel
Chaptered digest read. The digest does not name the Government Code or Water Code sections, a 2028 phase-in, or workforce disclosures, so those were removed; check the section text for full contents of the required information. Cal Cities sought a veto. Part of the data center package (with AB 2383).
Source guidance for local agencies
Cal Cities (opposed, requested a veto) says conditioning permits on this information creates new challenges for cities and advises building the water supply requirements into application checklists. County of Orange and KP Public Affairs advise setting cost-recovery fees and coordinating with water suppliers; Holland & Knight notes it reaches ministerial permits.
Sources and provenance
This overview organizes findings supplied in the California 2026 localities workbook. Source links and commentary were carried over from that workbook; they have not been independently verified for this article. Association and law-firm summaries are secondary commentary, not controlling law. Consult the official text before relying on an interpretation.
- California Legislative Information — chaptered bill text and digestOfficial
- League of California Cities (Cal Cities)Local government association · 2026-06-24
Bars approval of data centers without specified water supply planning. - League of California Cities (Cal Cities)Local government association · 2026-09-02
Bars cities and counties from approving a data center unless the applicant supplies specified water-supply planning information.
Local guidance: Cal Cities encouraged cities to send Governor letters and contact their regional public affairs manager before Sept. 30. - RCRCLocal government association · 2026-09-04
Data center permitting and water. - County of Orange Office of Legislative AffairsOfficial · 2026-09-11
Data center permitting tied to water supply assessments. - County of Orange Office of Legislative AffairsOfficial · 2026-09-24
Cities and counties may not approve data center permits without a water supply assessment; water scarcity plan from 1/1/2028; developer pays water infrastructure costs; local fees allowed.
Local guidance: Set cost-recovery fees and coordinate with water suppliers. - Mayer BrownLaw firm · 2026-09-28
From Jan. 1, 2028 data center applicants must file a water-supply assessment and water scarcity plan, disclose workforce needs and pay full water infrastructure costs. - KP Public AffairsPolicy/news · 2026-10-02
Local agency may not approve a new or expanded data center unless the applicant provides a water supply assessment, a water scarcity plan (from Jan. 1, 2028), and workforce-need disclosures.
Local guidance: Add water supply assessment and disclosures to data center application checklists. - Holland & Knight LLPLaw firm · 2026-10-05
Cities and counties, including charter cities, may not approve a discretionary or ministerial permit for building or expanding a data center that raises peak water use unless the applicant provides a water supply assessment, a water scarcity plan from 2028 and workforce and water efficiency information.
Local guidance: Add these items to application checklists. - League of California Cities (Cal Cities)Local government association · 2026-10-07
Bars cities and counties from approving a data center unless the applicant supplies specified water-supply planning information.
Local guidance: Cities processing data center applications should build the water-supply information requirement into application checklists. - Brownstein Hyatt Farber Schreck (via JDSupra)Law firm · 2026-10-07
Requires water planning before local approval of data centers and gives local governments and water suppliers information to evaluate data center water demand.
Frequently asked questions
What does AB 2469 do?
Bars a city or county from approving a discretionary or ministerial permit or other entitlement for building a data center, or expanding one in a way that raises maximum peak water use, unless the applicant has supplied prescribed information, including a water scarcity plan and a water supply assessment. The applicant must also take responsibility for the full cost of any water conveyance, treatment, storage or distribution improvements the water supplier says are needed. The Legislature finds this is a statewide concern that reaches charter cities.
Which local agencies or staff are affected?
All cities and counties, including charter cities
What should local government staff do next?
Planning and building staff: add to data center application checklists the water scarcity plan, water supply assessment and other prescribed information, plus a showing that the applicant will pay the full cost of water conveyance, treatment, storage or distribution improvements set by the water supplier, and withhold discretionary or ministerial approval until these are provided. Amend zoning and permit procedures and cost-recovery fees; coordinate with water suppliers.
Prepared as an informational guide for local government professionals. Confirm statutory requirements, local applicability, and current law with qualified agency counsel.
Published by Legislaide Editorial Team. Workbook-based legislative overview. Sources, review, and corrections policy. Source reference record (JSON).