AB 2518: San Diego Gas and Electric Company: energization pilot program — California Local Government Guide

Bill: AB 2518Effective: Jan 1, 2027 (non-urgency)

Until Jan 1, 2030, requires SDG&E to energize construction-ready projects within timeframes set in the statute and to include that energization data in its biannual reporting to the CPUC. The digest does not define the project categories or the day counts. Local governments are indirect beneficiaries as project sponsors and have no duties.

CaliforniaLocal GovernmentAB 2518Environmental Quality (Water, Energy, Waste, Climate)2026 California Law

Key takeaways

  • Until Jan 1, 2030, requires SDG&E to energize construction-ready projects within timeframes set in the statute and to include that energization data in its biannual reporting to the CPUC.
  • The digest does not define the project categories or the day counts.
  • Local governments are indirect beneficiaries as project sponsors and have no duties.

AB 2518 — Ch. 616, Stats. 2026. This guide is written for California local government staff and distinguishes the law's direct requirements from source commentary and possible local implications.

At a glance

Bill and chapterAB 2518 · Ch. 616, Stats. 2026
Subject areaEnvironmental Quality (Water, Energy, Waste, Climate)
Local impactInformational or monitoring
Action classNone
Workbook priority1.0 (scale: 5 highest)
Effective dateJan 1, 2027 (non-urgency); SDG&E energization requirement and added reporting run until Jan 1, 2030
Who is affectedSan Diego Gas and Electric Company and its customers, including local government project sponsors in its service territory

What the measure changes

Until Jan 1, 2030, requires SDG&E to energize construction-ready projects within timeframes set in the statute and to include that energization data in its biannual reporting to the CPUC. The digest does not define the project categories or the day counts. Local governments are indirect beneficiaries as project sponsors and have no duties.

The chaptered bill text controls; the Legislative Counsel’s Digest is a summary of the statute. This article translates the workbook’s findings into an implementation-focused overview and does not replace the statute or jurisdiction-specific legal advice.

Who this matters to in city or county government

Covered entities and scope: San Diego Gas and Electric Company and its customers, including local government project sponsors in its service territory

Population or other scope limit: SDG&E service territory; pilot ends Jan 1, 2030

Departments and roles identified in the workbook:

  • Building/Permits
  • Public Works/Engineering

Charter-city note: N/A

What local governments need to know

Mandatory local action: The workbook does not identify a new required city or county action. No local duty; cities and the county in the SDG&E service area with construction-ready projects should note that SDG&E must meet set energization timeframes through Jan 1, 2030.

Code review: No

Potentially affected code or policy areas: None

Preemption or local authority: No

New local requirement: No

Implementation roadmap

  1. Determine whether the agency is within the law's scope: San Diego Gas and Electric Company and its customers, including local government project sponsors in its service territory
  2. Decide whether any optional authority, funding, revenue, or operational opportunity is relevant to local policy.
  3. Check existing code and procedures for a conflict or an implementation opportunity before changing local practice.
  4. Calendar relevant dates and monitor state guidance: Jan 1, 2027 (non-urgency); SDG&E energization requirement and added reporting run until Jan 1, 2030

Key dates and deadlines

  • General effective date and deadlines: Jan 1, 2027 (non-urgency); SDG&E energization requirement and added reporting run until Jan 1, 2030

Implementation and compliance considerations

Implementation areaReviewWhat staff should verify
Local impact classificationInformational or monitoringWorkbook action class: None.
Scope and coverageConfirmSDG&E service territory; pilot ends Jan 1, 2030
Effective datesCalendarJan 1, 2027 (non-urgency); SDG&E energization requirement and added reporting run until Jan 1, 2030

Enforcement and reimbursement

CPUC oversight; violations of CPUC orders are crimes; state-mandated local program, but the digest says no reimbursement is required

Issues to confirm with agency counsel

Chaptered digest confirms the Jan 1, 2030 sunset. The earlier 40, 55 and 70 business day figures, project categories (such as fire stations) and Pub. Util. Code 769.7 cite are not in the digest and were removed; confirm them in the statute text.

Sources and provenance

This overview organizes findings supplied in the California 2026 localities workbook. Source links and commentary were carried over from that workbook; they have not been independently verified for this article. Association and law-firm summaries are secondary commentary, not controlling law. Consult the official text before relying on an interpretation.

Frequently asked questions

What does AB 2518 do?

Until Jan 1, 2030, requires SDG&E to energize construction-ready projects within timeframes set in the statute and to include that energization data in its biannual reporting to the CPUC. The digest does not define the project categories or the day counts. Local governments are indirect beneficiaries as project sponsors and have no duties.

Which local agencies or staff are affected?

San Diego Gas and Electric Company and its customers, including local government project sponsors in its service territory

What should local government staff do next?

Review whether optional authority or indirect impacts are relevant, and confirm the chaptered text.

Prepared as an informational guide for local government professionals. Confirm statutory requirements, local applicability, and current law with qualified agency counsel.