Key takeaways
- An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days.
- For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required.
- Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it.
- Changes are declared a statewide concern and apply to charter cities.
SB 1014 — Ch. 806, Stats. 2026. This guide is written for California local government staff and distinguishes the law's direct requirements from source commentary and possible local implications.
At a glance
| Bill and chapter | SB 1014 · Ch. 806, Stats. 2026 |
|---|---|
| Subject area | Housing, Land Use & Economic Development |
| Local impact | Required: administrative action |
| Action class | Operational only |
| Workbook priority | 4.0 (scale: 5 highest) |
| Effective date | Jan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists |
| Who is affected | All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements |
What the measure changes
An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days. For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required. Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it. Changes are declared a statewide concern and apply to charter cities.
The chaptered bill text controls; the Legislative Counsel’s Digest is a summary of the statute. This article translates the workbook’s findings into an implementation-focused overview and does not replace the statute or jurisdiction-specific legal advice.
Who this matters to in city or county government
Covered entities and scope: All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements
Population or other scope limit: Housing development projects (preliminary applications or applications, and post-entitlement phase permits)
Departments and roles identified in the workbook:
- Planning/Zoning
- Public Works/Engineering
- Building/Permits
- Housing
- Utilities (Water/Wastewater/Solid Waste/Energy)
- City/County Attorney
Charter-city note: Applies (statewide concern declared)
What local governments need to know
Planning and public works: build a template and process to give an applicant, on request, a preliminary estimate of required improvements within 30 business days of the request, and an itemized list of all onsite and offsite improvements within 30 business days after a post-entitlement permit application is deemed complete; update application checklists and coordinate with other public agencies that require improvements, since applicants may request a list of the types of improvements within 30 days of submission.
Operational change: Planning and public works build a process and template to give housing applicants, on request, a preliminary estimate of required improvements within 30 business days, and an itemized onsite and offsite improvement list within 30 business days after a post-entitlement permit application is complete; update checklists and coordinate with other agencies that impose improvements.
Code review: Yes
Potentially affected code or policy areas: Permit Streamlining Act application checklists; Subdivision and improvement standards; Post-entitlement permit procedures; Preliminary application procedures
Preemption or local authority: No
New local requirement: Yes
Implementation roadmap
- Confirm the agency is covered: All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements Scope limits: Housing development projects (preliminary applications or applications, and post-entitlement phase permits)
- Assign a lead and supporting roles from the affected departments: Planning/Zoning, Public Works/Engineering, Building/Permits, Housing, Utilities (Water/Wastewater/Solid Waste/Energy), City/County Attorney.
- Update staff workflow, forms, notices, contracting, reporting, or training as applicable: Planning and public works build a process and template to give housing applicants, on request, a preliminary estimate of required improvements within 30 business days, and an itemized onsite and offsite improvement list within 30 business days after a post-entitlement permit application is complete; update checklists and coordinate with other agencies that impose improvements.
- Calendar and verify the applicable dates: Jan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists
Key dates and deadlines
- General effective date and deadlines: Jan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists
- Code change deadline: Not applicable
Implementation and compliance considerations
| Implementation area | Review | What staff should verify |
|---|---|---|
| Local impact classification | Required: administrative action | Workbook action class: Operational only. |
| Scope and coverage | Confirm | Housing development projects (preliminary applications or applications, and post-entitlement phase permits) |
| Effective dates | Calendar | Jan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists |
Enforcement and reimbursement
No penalty stated; state-mandated local program, with no reimbursement required for a specified reason; the bill does not relieve the agency of existing requirements before applying an improvement that was not in effect when a preliminary application was submitted
Issues to confirm with agency counsel
Interacts with preliminary application rights for housing development projects and the post-entitlement phase permit process. The digest says the bill does not relieve agencies of existing requirements before applying improvements not in effect at preliminary application. Check how other public agencies (special districts, utilities) that require improvements are handled in the full text.
Source guidance for local agencies
Coblentz says staff will need repeatable templates, cost estimate processes and coordination with utilities and other agencies; Allen Matkins stresses the 30 day list requirement and a bar on later additions (the bar on later additions is not described in the digest; confirm in the text); California YIMBY, the sponsor-side voice, frames it as more transparent and predictable fees.
Sources and provenance
This overview organizes findings supplied in the California 2026 localities workbook. Source links and commentary were carried over from that workbook; they have not been independently verified for this article. Association and law-firm summaries are secondary commentary, not controlling law. Consult the official text before relying on an interpretation.
- California Legislative Information — chaptered bill text and digestOfficial
- Office of Governor Gavin NewsomOfficial · 2026-09-29
Listed as preliminary estimate of required improvements for development projects. - California YIMBYPolicy/news · 2026-09-30
Sponsor-side description: the bill makes local housing fees and required improvements more transparent and predictable for applicants. - Allen MatkinsLaw firm · 2026-10-01
Requires an itemized list of onsite and offsite improvements within 30 days after a post-entitlement permit application is deemed complete and bars later additions with limited exceptions; also requires a good-faith improvement estimate within 30 business days of a complete preliminary application when requested. - Coblentz LawLaw firm · 2026-10-06
Housing applicants can ask for a nonbinding good-faith estimate of required onsite and offsite improvements and their cost, due within 30 business days of an SB 330 preliminary application or the development application. After a post-entitlement permit application is complete, the agency must list all required improvements within 30 business days and generally cannot add omitted ones later, except for a specific health or safety impact, applicant-requested changes, or CEQA for discretionary permits. Other agencies and utilities have 30 business days to respond to list requests.
Local guidance: Staff will need a repeatable process and templates for improvement lists and cost estimates, and coordination with utilities and other agencies.
Frequently asked questions
What does SB 1014 do?
An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days. For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required. Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it. Changes are declared a statewide concern and apply to charter cities.
Which local agencies or staff are affected?
All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements
What should local government staff do next?
Planning and public works: build a template and process to give an applicant, on request, a preliminary estimate of required improvements within 30 business days of the request, and an itemized list of all onsite and offsite improvements within 30 business days after a post-entitlement permit application is deemed complete; update application checklists and coordinate with other public agencies that require improvements, since applicants may request a list of the types of improvements within 30 days of submission.
Prepared as an informational guide for local government professionals. Confirm statutory requirements, local applicability, and current law with qualified agency counsel.
Published by Legislaide Editorial Team. Workbook-based legislative overview. Sources, review, and corrections policy. Source reference record (JSON).