Bill: SB 1014Effective: Jan 1, 2027 (regular statute

An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days. For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required. Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it. Changes are declared a statewide concern and apply to charter cities.

CaliforniaLocal GovernmentSB 1014Housing, Land Use & Economic Development2026 California Law

Key takeaways

  • An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days.
  • For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required.
  • Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it.
  • Changes are declared a statewide concern and apply to charter cities.

SB 1014 — Ch. 806, Stats. 2026. This guide is written for California local government staff and distinguishes the law's direct requirements from source commentary and possible local implications.

At a glance

Bill and chapterSB 1014 · Ch. 806, Stats. 2026
Subject areaHousing, Land Use & Economic Development
Local impactRequired: administrative action
Action classOperational only
Workbook priority4.0 (scale: 5 highest)
Effective dateJan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists
Who is affectedAll cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements

What the measure changes

An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days. For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required. Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it. Changes are declared a statewide concern and apply to charter cities.

The chaptered bill text controls; the Legislative Counsel’s Digest is a summary of the statute. This article translates the workbook’s findings into an implementation-focused overview and does not replace the statute or jurisdiction-specific legal advice.

Who this matters to in city or county government

Covered entities and scope: All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements

Population or other scope limit: Housing development projects (preliminary applications or applications, and post-entitlement phase permits)

Departments and roles identified in the workbook:

  • Planning/Zoning
  • Public Works/Engineering
  • Building/Permits
  • Housing
  • Utilities (Water/Wastewater/Solid Waste/Energy)
  • City/County Attorney

Charter-city note: Applies (statewide concern declared)

What local governments need to know

Planning and public works: build a template and process to give an applicant, on request, a preliminary estimate of required improvements within 30 business days of the request, and an itemized list of all onsite and offsite improvements within 30 business days after a post-entitlement permit application is deemed complete; update application checklists and coordinate with other public agencies that require improvements, since applicants may request a list of the types of improvements within 30 days of submission.

Operational change: Planning and public works build a process and template to give housing applicants, on request, a preliminary estimate of required improvements within 30 business days, and an itemized onsite and offsite improvement list within 30 business days after a post-entitlement permit application is complete; update checklists and coordinate with other agencies that impose improvements.

Code review: Yes

Potentially affected code or policy areas: Permit Streamlining Act application checklists; Subdivision and improvement standards; Post-entitlement permit procedures; Preliminary application procedures

Preemption or local authority: No

New local requirement: Yes

Implementation roadmap

  1. Confirm the agency is covered: All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements Scope limits: Housing development projects (preliminary applications or applications, and post-entitlement phase permits)
  2. Assign a lead and supporting roles from the affected departments: Planning/Zoning, Public Works/Engineering, Building/Permits, Housing, Utilities (Water/Wastewater/Solid Waste/Energy), City/County Attorney.
  3. Update staff workflow, forms, notices, contracting, reporting, or training as applicable: Planning and public works build a process and template to give housing applicants, on request, a preliminary estimate of required improvements within 30 business days, and an itemized onsite and offsite improvement list within 30 business days after a post-entitlement permit application is complete; update checklists and coordinate with other agencies that impose improvements.
  4. Calendar and verify the applicable dates: Jan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists

Key dates and deadlines

  • General effective date and deadlines: Jan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists
  • Code change deadline: Not applicable

Implementation and compliance considerations

Implementation areaReviewWhat staff should verify
Local impact classificationRequired: administrative actionWorkbook action class: Operational only.
Scope and coverageConfirmHousing development projects (preliminary applications or applications, and post-entitlement phase permits)
Effective datesCalendarJan 1, 2027 (regular statute; digest has no urgency clause); 30 business day deadlines for estimates and itemized lists

Enforcement and reimbursement

No penalty stated; state-mandated local program, with no reimbursement required for a specified reason; the bill does not relieve the agency of existing requirements before applying an improvement that was not in effect when a preliminary application was submitted

Issues to confirm with agency counsel

Interacts with preliminary application rights for housing development projects and the post-entitlement phase permit process. The digest says the bill does not relieve agencies of existing requirements before applying improvements not in effect at preliminary application. Check how other public agencies (special districts, utilities) that require improvements are handled in the full text.

Source guidance for local agencies

Coblentz says staff will need repeatable templates, cost estimate processes and coordination with utilities and other agencies; Allen Matkins stresses the 30 day list requirement and a bar on later additions (the bar on later additions is not described in the digest; confirm in the text); California YIMBY, the sponsor-side voice, frames it as more transparent and predictable fees.

Sources and provenance

This overview organizes findings supplied in the California 2026 localities workbook. Source links and commentary were carried over from that workbook; they have not been independently verified for this article. Association and law-firm summaries are secondary commentary, not controlling law. Consult the official text before relying on an interpretation.

  • California Legislative Information — chaptered bill text and digestOfficial
  • Office of Governor Gavin NewsomOfficial · 2026-09-29
    Listed as preliminary estimate of required improvements for development projects.
  • California YIMBYPolicy/news · 2026-09-30
    Sponsor-side description: the bill makes local housing fees and required improvements more transparent and predictable for applicants.
  • Allen MatkinsLaw firm · 2026-10-01
    Requires an itemized list of onsite and offsite improvements within 30 days after a post-entitlement permit application is deemed complete and bars later additions with limited exceptions; also requires a good-faith improvement estimate within 30 business days of a complete preliminary application when requested.
  • Coblentz LawLaw firm · 2026-10-06
    Housing applicants can ask for a nonbinding good-faith estimate of required onsite and offsite improvements and their cost, due within 30 business days of an SB 330 preliminary application or the development application. After a post-entitlement permit application is complete, the agency must list all required improvements within 30 business days and generally cannot add omitted ones later, except for a specific health or safety impact, applicant-requested changes, or CEQA for discretionary permits. Other agencies and utilities have 30 business days to respond to list requests.
    Local guidance: Staff will need a repeatable process and templates for improvement lists and cost estimates, and coordination with utilities and other agencies.

Frequently asked questions

What does SB 1014 do?

An applicant for a housing development project may ask, in a preliminary application or an application, for a preliminary estimate of required improvements, and the city or county must provide it within 30 business days. For improvements required by another public agency, the applicant can ask within 30 days of submission for a list of the types of improvements that may be required. Within 30 business days of deeming a post-entitlement phase permit application complete, the city or county must give an itemized list of all onsite and offsite improvements required before the permit issues or otherwise in connection with it. Changes are declared a statewide concern and apply to charter cities.

Which local agencies or staff are affected?

All cities, counties and cities and counties processing housing development projects; special districts and utilities that impose improvements

What should local government staff do next?

Planning and public works: build a template and process to give an applicant, on request, a preliminary estimate of required improvements within 30 business days of the request, and an itemized list of all onsite and offsite improvements within 30 business days after a post-entitlement permit application is deemed complete; update application checklists and coordinate with other public agencies that require improvements, since applicants may request a list of the types of improvements within 30 days of submission.

Prepared as an informational guide for local government professionals. Confirm statutory requirements, local applicability, and current law with qualified agency counsel.


Published by Legislaide Editorial Team. Workbook-based legislative overview. Sources, review, and corrections policy. Source reference record (JSON).