Key takeaways
- Until Jan 1, 2030, portable solar generation devices, as defined, are exempt from all interconnection requirements, including the rules of local publicly owned electric utilities.
- These utilities and investor-owned utilities may not require the customer to pay any fee or charge for the device or the power it feeds into a building, and among other limits may require only a simple online registration of address, make, model and size.
- From Jan 1, 2030, plug-in photovoltaic devices that do not meet the definition may not be sold.
SB 868 — Ch. 985, Stats. 2026. This guide is written for California local government staff and distinguishes the law's direct requirements from source commentary and possible local implications.
At a glance
| Bill and chapter | SB 868 · Ch. 985, Stats. 2026 |
|---|---|
| Subject area | Environmental Quality (Water, Energy, Waste, Climate) |
| Local impact | Limits or preempts local authority |
| Action class | Code and operational |
| Workbook priority | 3.0 (scale: 5 highest) |
| Effective date | Jan 1, 2027 (general effective date; not an urgency statute); interconnection exemption and fee prohibition run until Jan 1, 2030; sales ban on non-conforming plug-in solar devices starts Jan 1, 2030 |
| Who is affected | Local publicly owned electric utilities (city, district and county), investor-owned utilities, customers and device sellers |
What the measure changes
Until Jan 1, 2030, portable solar generation devices, as defined, are exempt from all interconnection requirements, including the rules of local publicly owned electric utilities. These utilities and investor-owned utilities may not require the customer to pay any fee or charge for the device or the power it feeds into a building, and among other limits may require only a simple online registration of address, make, model and size. From Jan 1, 2030, plug-in photovoltaic devices that do not meet the definition may not be sold.
The chaptered bill text controls; the Legislative Counsel’s Digest is a summary of the statute. This article translates the workbook’s findings into an implementation-focused overview and does not replace the statute or jurisdiction-specific legal advice.
Who this matters to in city or county government
Covered entities and scope: Local publicly owned electric utilities (city, district and county), investor-owned utilities, customers and device sellers
Population or other scope limit: Portable solar generation devices as defined in the bill; exemptions and prohibitions run until Jan 1, 2030
Departments and roles identified in the workbook:
- Utilities (Water/Wastewater/Solid Waste/Energy)
- City Council/Board
- City/County Attorney
- Finance/Treasury/Tax
Charter-city note: Not stated
What local governments need to know
City- and district-owned electric utilities should have their governing boards and attorneys revise interconnection rules and tariffs so that qualifying portable plug-in solar devices are exempt from interconnection requirements and from any fees, charges or other customer requirements the bill bars until Jan 1, 2030; a simple online registration of address, make, model and size is optional.
Code or governing-body change: Condition: only for localities that operate a publicly owned electric utility; the governing board revises interconnection rules, tariffs and fee schedules to exempt qualifying portable solar devices from interconnection requirements and from fees or charges until Jan 1, 2030.
Operational change: Utility customer service staff stop applying interconnection steps and charges to qualifying devices and, if desired, set up a simple online registration for address, make, model and size.
Code review: Possibly
Potentially affected code or policy areas: Utilities rates and interconnection rules; Customer service rules and tariffs
Preemption or local authority: Yes
New local requirement: Yes
Implementation roadmap
- Confirm the agency is covered: Local publicly owned electric utilities (city, district and county), investor-owned utilities, customers and device sellers Scope limits: Portable solar generation devices as defined in the bill; exemptions and prohibitions run until Jan 1, 2030
- Assign a lead and supporting roles from the affected departments: Utilities (Water/Wastewater/Solid Waste/Energy), City Council/Board, City/County Attorney, Finance/Treasury/Tax.
- Review the relevant code, ordinance, plan, fee schedule, or governing-body policy: Condition: only for localities that operate a publicly owned electric utility; the governing board revises interconnection rules, tariffs and fee schedules to exempt qualifying portable solar devices from interconnection requirements and from fees or charges until Jan 1, 2030.
- Update staff workflow, forms, notices, contracting, reporting, or training as applicable: Utility customer service staff stop applying interconnection steps and charges to qualifying devices and, if desired, set up a simple online registration for address, make, model and size.
- Calendar and verify the applicable dates: Jan 1, 2027 (general effective date; not an urgency statute); interconnection exemption and fee prohibition run until Jan 1, 2030; sales ban on non-conforming plug-in solar devices starts Jan 1, 2030
Key dates and deadlines
- General effective date and deadlines: Jan 1, 2027 (general effective date; not an urgency statute); interconnection exemption and fee prohibition run until Jan 1, 2030; sales ban on non-conforming plug-in solar devices starts Jan 1, 2030
- Code change deadline: Jan 1, 2027
Implementation and compliance considerations
| Implementation area | Review | What staff should verify |
|---|---|---|
| Local impact classification | Limits or preempts local authority | Workbook action class: Code and operational. |
| Scope and coverage | Confirm | Portable solar generation devices as defined in the bill; exemptions and prohibitions run until Jan 1, 2030 |
| Effective dates | Calendar | Jan 1, 2027 (general effective date; not an urgency statute); interconnection exemption and fee prohibition run until Jan 1, 2030; sales ban on non-conforming plug-in solar devices starts Jan 1, 2030 |
Enforcement and reimbursement
A violation of a Public Utilities Commission requirement is a crime and new duties on local publicly owned utilities create a state-mandated local program; no reimbursement required for stated reasons
Issues to confirm with agency counsel
Digest read from the chaptered text. The digest does not address city building permits or electrical inspection for plug-in devices, and does not give a wattage limit; CALBO opposed the bill, so building officials should confirm how permits and inspections apply. The digest does not address charter cities.
Source guidance for local agencies
CALBO opposed the bill. KP Public Affairs notes the exemption from interconnection fees and the 2030 sales ban for nonconforming devices.
Sources and provenance
This overview organizes findings supplied in the California 2026 localities workbook. Source links and commentary were carried over from that workbook; they have not been independently verified for this article. Association and law-firm summaries are secondary commentary, not controlling law. Consult the official text before relying on an interpretation.
- California Legislative Information — chaptered bill text and digestOfficial
- California Building Officials (CALBO)Local government association · 2026-09-04
Plug and Play Solar Act exempting portable plug-in solar devices from interconnection rules. - Governor of California (gov.ca.gov)Official · 2026-09-30
Portable plug-in solar devices. - KP Public AffairsPolicy/news · 2026-10-02
Exempts portable 120-volt plug-in solar from utility interconnection fees; bans sale of non-conforming devices from 2030.
Frequently asked questions
What does SB 868 do?
Until Jan 1, 2030, portable solar generation devices, as defined, are exempt from all interconnection requirements, including the rules of local publicly owned electric utilities. These utilities and investor-owned utilities may not require the customer to pay any fee or charge for the device or the power it feeds into a building, and among other limits may require only a simple online registration of address, make, model and size. From Jan 1, 2030, plug-in photovoltaic devices that do not meet the definition may not be sold.
Which local agencies or staff are affected?
Local publicly owned electric utilities (city, district and county), investor-owned utilities, customers and device sellers
What should local government staff do next?
City- and district-owned electric utilities should have their governing boards and attorneys revise interconnection rules and tariffs so that qualifying portable plug-in solar devices are exempt from interconnection requirements and from any fees, charges or other customer requirements the bill bars until Jan 1, 2030; a simple online registration of address, make, model and size is optional.
Prepared as an informational guide for local government professionals. Confirm statutory requirements, local applicability, and current law with qualified agency counsel.
Published by Legislaide Editorial Team. Workbook-based legislative overview. Sources, review, and corrections policy. Source reference record (JSON).